Dominican Republic vs Indonesia: Dealing with construction permits: Time
Dealing with construction permits: Time over time
- Dominican Republic
- Indonesia
How they compare
Dominican Republic currently reports 206 days against 200.13 days in Indonesia, a difference of 5.87 days.
The two have swapped places 2 times across 15 shared years of data; in 2005 it was Dominican Republic ahead.
Dominican Republic ranks 34th and Indonesia ranks 35th of 185 countries.
Dominican Republic has averaged higher in every one of the 2 decades both report.
Head to head by decade
| Decade | Dominican Republic | Indonesia | Difference | Ahead |
|---|---|---|---|---|
| 2000s | 223 days | 191 days | 32 days | Dominican Republic |
| 2010s | 203.5 days | 197.45 days | 6.05 days | Dominican Republic |
Averages of every year both report within each decade.
Frequently asked questions
- Which has higher dealing with construction permits: time, Dominican Republic or Indonesia?
- Dominican Republic, at 206 days against 200.13 days in Indonesia as of 2019.
- What is the difference in dealing with construction permits: time between Dominican Republic and Indonesia?
- 5.87 days, with Dominican Republic ahead.
- How many years of comparable data are there for Dominican Republic and Indonesia?
- 15 years are reported by both, from 2005 to 2019.
- How do Dominican Republic and Indonesia rank globally for dealing with construction permits: time?
- Dominican Republic ranks 34th and Indonesia ranks 35th of 185 countries.
- Where does this data come from?
- The World Bank, published as Dealing with construction permits: Time (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.
Individual pages
About this data
The time captures the median duration that local experts indicate is necessary to complete a procedure in practice. It is calculated in calendar days. The time estimates of all procedures are added to calculate the total time required to complete each procedure, taking into account simultaneity of processes. It is assumed that the minimum time required for each procedure is one day, except for procedures that can be fully completed online, for which the time required is recorded as half a day.