Botswana vs Mauritius: Time required to deal with construction permits

Botswana
145 days
in 2012
Mauritius
143 days
in 2012
Botswana rank
30th
Mauritius rank
31st

Time required to deal with construction permits over time

  • Botswana
  • Mauritius
050100150200200520082012

How they compare

Botswana currently reports 145 days against 143 days in Mauritius, a difference of 2 days.

The two have swapped places 1 time across 8 shared years of data; in 2005 it was Mauritius ahead.

Botswana ranks 30th and Mauritius ranks 31st of 50 countries.

Across the 2 decades both report, Botswana averaged higher in 1 and Mauritius in 1.

Head to head by decade

Decade Botswana Mauritius Difference Ahead
2000s 139 days 159.8 days 20.8 days Mauritius
2010s 145 days 143 days 2 days Botswana

Averages of every year both report within each decade.

Frequently asked questions

Which has higher time required to deal with construction permits, Botswana or Mauritius?
Botswana, at 145 days against 143 days in Mauritius as of 2012.
What is the difference in time required to deal with construction permits between Botswana and Mauritius?
2 days, with Botswana ahead.
How many years of comparable data are there for Botswana and Mauritius?
8 years are reported by both, from 2005 to 2012.
How do Botswana and Mauritius rank globally for time required to deal with construction permits?
Botswana ranks 30th and Mauritius ranks 31st of 50 countries.
Where does this data come from?
World Bank, Doing Business project (http://www.doingbusiness.org/), published as Time required to deal with construction permits (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.

Individual pages

About this data

Indicator
Time required to deal with construction permits (days)
Unit
days
Source
World Bank, Doing Business project (http://www.doingbusiness.org/)
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
56 places, 447 data points, 2005–2012
Last refreshed

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.