Azerbaijan vs Eswatini: Dealing with construction permits: Time

Azerbaijan
116 days
in 2019
Eswatini
116 days
in 2019
Azerbaijan rank
118th
Eswatini rank
118th

Dealing with construction permits: Time over time

  • Azerbaijan
  • Eswatini
050100150200200520122019

How they compare

Azerbaijan currently reports 116 days against 116 days in Eswatini, a difference of 0 days.

The two have swapped places 1 time across 15 shared years of data; in 2005 it was Azerbaijan ahead.

Azerbaijan ranks 118th and Eswatini ranks 118th of 185 countries.

Azerbaijan has averaged higher in every one of the 2 decades both report.

Head to head by decade

Decade Azerbaijan Eswatini Difference Ahead
2000s 204 days 116 days 88 days Azerbaijan
2010s 182.2 days 116 days 66.2 days Azerbaijan

Averages of every year both report within each decade.

Frequently asked questions

Which has higher dealing with construction permits: time, Azerbaijan or Eswatini?
Azerbaijan, at 116 days against 116 days in Eswatini as of 2019.
What is the difference in dealing with construction permits: time between Azerbaijan and Eswatini?
0 days, with Azerbaijan ahead.
How many years of comparable data are there for Azerbaijan and Eswatini?
15 years are reported by both, from 2005 to 2019.
How do Azerbaijan and Eswatini rank globally for dealing with construction permits: time?
Azerbaijan ranks 118th and Eswatini ranks 118th of 185 countries.
Where does this data come from?
The World Bank, published as Dealing with construction permits: Time (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.

Individual pages

About this data

Indicator
Dealing with construction permits: Time (days)
Unit
days
Source
World Bank
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
187 places, 2,740 data points, 2005–2019
Last refreshed

The time captures the median duration that local experts indicate is necessary to complete a procedure in practice. It is calculated in calendar days. The time estimates of all procedures are added to calculate the total time required to complete each procedure, taking into account simultaneity of processes. It is assumed that the minimum time required for each procedure is one day, except for procedures that can be fully completed online, for which the time required is recorded as half a day.