Benin vs Liberia: Dealing with construction permits: Time
Dealing with construction permits: Time over time
- Benin
- Liberia
How they compare
Benin currently reports 88 days against 87 days in Liberia, a difference of 1 days.
Across all 14 years both countries report, Benin has been ahead every year.
Benin ranks 155th and Liberia ranks 158th of 185 countries.
Benin has averaged higher in every one of the 2 decades both report.
Head to head by decade
| Decade | Benin | Liberia | Difference | Ahead |
|---|---|---|---|---|
| 2000s | 277.5 days | 121 days | 156.5 days | Benin |
| 2010s | 126.2 days | 87 days | 39.2 days | Benin |
Averages of every year both report within each decade.
Frequently asked questions
- Which has higher dealing with construction permits: time, Benin or Liberia?
- Benin, at 88 days against 87 days in Liberia as of 2019.
- What is the difference in dealing with construction permits: time between Benin and Liberia?
- 1 days, with Benin ahead.
- How many years of comparable data are there for Benin and Liberia?
- 14 years are reported by both, from 2006 to 2019.
- How do Benin and Liberia rank globally for dealing with construction permits: time?
- Benin ranks 155th and Liberia ranks 158th of 185 countries.
- Where does this data come from?
- The World Bank, published as Dealing with construction permits: Time (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.
Individual pages
About this data
The time captures the median duration that local experts indicate is necessary to complete a procedure in practice. It is calculated in calendar days. The time estimates of all procedures are added to calculate the total time required to complete each procedure, taking into account simultaneity of processes. It is assumed that the minimum time required for each procedure is one day, except for procedures that can be fully completed online, for which the time required is recorded as half a day.