Benin vs Qatar: Dealing with construction permits: Time

Benin
88 days
in 2019
Qatar
87.5 days
in 2019
Benin rank
155th
Qatar rank
157th

Dealing with construction permits: Time over time

  • Benin
  • Qatar
100200300200520122019

How they compare

Benin currently reports 88 days against 87.5 days in Qatar, a difference of 0.5 days.

Across all 13 years both countries report, Benin has been ahead every year.

Benin ranks 155th and Qatar ranks 157th of 185 countries.

Benin has averaged higher in every one of the 2 decades both report.

Head to head by decade

Decade Benin Qatar Difference Ahead
2000s 290.67 days 62 days 228.67 days Benin
2010s 126.2 days 74.75 days 51.45 days Benin

Averages of every year both report within each decade.

Frequently asked questions

Which has higher dealing with construction permits: time, Benin or Qatar?
Benin, at 88 days against 87.5 days in Qatar as of 2019.
What is the difference in dealing with construction permits: time between Benin and Qatar?
0.5 days, with Benin ahead.
How many years of comparable data are there for Benin and Qatar?
13 years are reported by both, from 2007 to 2019.
How do Benin and Qatar rank globally for dealing with construction permits: time?
Benin ranks 155th and Qatar ranks 157th of 185 countries.
Where does this data come from?
The World Bank, published as Dealing with construction permits: Time (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.

Individual pages

About this data

Indicator
Dealing with construction permits: Time (days)
Unit
days
Source
World Bank
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
187 places, 2,740 data points, 2005–2019
Last refreshed

The time captures the median duration that local experts indicate is necessary to complete a procedure in practice. It is calculated in calendar days. The time estimates of all procedures are added to calculate the total time required to complete each procedure, taking into account simultaneity of processes. It is assumed that the minimum time required for each procedure is one day, except for procedures that can be fully completed online, for which the time required is recorded as half a day.