Sudan vs Uruguay: Dealing with construction permits: Time

Sudan
255 days
in 2019
Uruguay
265 days
in 2019
Sudan rank
16th
Uruguay rank
14th

Dealing with construction permits: Time over time

  • Sudan
  • Uruguay
0100200300200520122019

How they compare

Uruguay currently reports 265 days against 255 days in Sudan, a difference of 10 days.

The two have swapped places 1 time across 15 shared years of data; in 2005 it was Sudan ahead.

Sudan ranks 16th and Uruguay ranks 14th of 185 countries.

Across the 2 decades both report, Sudan averaged higher in 1 and Uruguay in 1.

Head to head by decade

Decade Sudan Uruguay Difference Ahead
2000s 274 days 265 days 9 days Sudan
2010s 255 days 265 days 10 days Uruguay

Averages of every year both report within each decade.

Frequently asked questions

Which has higher dealing with construction permits: time, Sudan or Uruguay?
Uruguay, at 265 days against 255 days in Sudan as of 2019.
What is the difference in dealing with construction permits: time between Sudan and Uruguay?
10 days, with Uruguay ahead.
How many years of comparable data are there for Sudan and Uruguay?
15 years are reported by both, from 2005 to 2019.
How do Sudan and Uruguay rank globally for dealing with construction permits: time?
Sudan ranks 16th and Uruguay ranks 14th of 185 countries.
Where does this data come from?
The World Bank, published as Dealing with construction permits: Time (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.

Individual pages

About this data

Indicator
Dealing with construction permits: Time (days)
Unit
days
Source
World Bank
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
187 places, 2,740 data points, 2005–2019
Last refreshed

The time captures the median duration that local experts indicate is necessary to complete a procedure in practice. It is calculated in calendar days. The time estimates of all procedures are added to calculate the total time required to complete each procedure, taking into account simultaneity of processes. It is assumed that the minimum time required for each procedure is one day, except for procedures that can be fully completed online, for which the time required is recorded as half a day.