Africa vs Angola: Time required to deal with construction permits

Africa
193.58 days
in 2012
Angola
348 days
in 2012
Africa rank
5th
Angola rank
4th

Time required to deal with construction permits over time

  • Africa
  • Angola
0100200300200520082012

How they compare

Angola currently reports 348 days against 193.58 days in Africa, a difference of 154.42 days.

That makes Angola's figure about 1.8 times Africa's.

Across all 8 years both countries report, Angola has been ahead every year.

Africa ranks 5th and Angola ranks 4th of 6 groups.

Angola has averaged higher in every one of the 2 decades both report.

Head to head by decade

Decade Africa Angola Difference Ahead
2000s 219.12 days 321 days 101.88 days Angola
2010s 196.25 days 330 days 133.75 days Angola

Averages of every year both report within each decade.

Frequently asked questions

Which has higher time required to deal with construction permits, Africa or Angola?
Angola, at 348 days against 193.58 days in Africa as of 2012.
What is the difference in time required to deal with construction permits between Africa and Angola?
154.42 days, with Angola ahead.
How many years of comparable data are there for Africa and Angola?
8 years are reported by both, from 2005 to 2012.
How do Africa and Angola rank globally for time required to deal with construction permits?
Africa ranks 5th and Angola ranks 4th of 6 groups.
Where does this data come from?
World Bank, Doing Business project (http://www.doingbusiness.org/), published as Time required to deal with construction permits (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.

Individual pages

Share, cite or embed this page

Cite this page

Africa vs Angola: Time required to deal with construction permits. Statizoid, drawing on World Bank, Doing Business project (http://www.doingbusiness.org/). Retrieved 26 August 2026, from https://private-sector.statizoid.com/compare/time-required-to-deal-with-construction-permits-days/africa/angola/

Embed or link this data

Paste this into a page to link back to these figures. The data itself is free to reuse under CC BY 4.0 (World Bank Open Data); please keep the attribution.

<a href="https://private-sector.statizoid.com/compare/time-required-to-deal-with-construction-permits-days/africa/angola/">Africa vs Angola: Time required to deal with construction permits</a> — Statizoid

About this data

Indicator
Time required to deal with construction permits (days)
Unit
days
Source
World Bank, Doing Business project (http://www.doingbusiness.org/)
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
56 places, 447 data points, 2005–2012
Last refreshed

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.