Algeria vs Niger: Time required to deal with construction permits

Algeria
281 days
in 2012
Niger
326 days
in 2012
Algeria rank
9th
Niger rank
6th

Time required to deal with construction permits over time

  • Algeria
  • Niger
0100200300200520082012

How they compare

Niger currently reports 326 days against 281 days in Algeria, a difference of 45 days.

That makes Niger's figure about 1.2 times Algeria's.

Across all 8 years both countries report, Niger has been ahead every year.

Algeria ranks 9th and Niger ranks 6th of 50 countries.

Niger has averaged higher in every one of the 2 decades both report.

Head to head by decade

Decade Algeria Niger Difference Ahead
2000s 281 days 327.8 days 46.8 days Niger
2010s 281 days 326 days 45 days Niger

Averages of every year both report within each decade.

Frequently asked questions

Which has higher time required to deal with construction permits, Algeria or Niger?
Niger, at 326 days against 281 days in Algeria as of 2012.
What is the difference in time required to deal with construction permits between Algeria and Niger?
45 days, with Niger ahead.
How many years of comparable data are there for Algeria and Niger?
8 years are reported by both, from 2005 to 2012.
How do Algeria and Niger rank globally for time required to deal with construction permits?
Algeria ranks 9th and Niger ranks 6th of 50 countries.
Where does this data come from?
World Bank, Doing Business project (http://www.doingbusiness.org/), published as Time required to deal with construction permits (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.

Individual pages

Share, cite or embed this page

Cite this page

Algeria vs Niger: Time required to deal with construction permits. Statizoid, drawing on World Bank, Doing Business project (http://www.doingbusiness.org/). Retrieved 17 August 2026, from https://private-sector.statizoid.com/compare/time-required-to-deal-with-construction-permits-days/algeria/niger/

Embed or link this data

Paste this into a page to link back to these figures. The data itself is free to reuse under CC BY 4.0 (World Bank Open Data); please keep the attribution.

<a href="https://private-sector.statizoid.com/compare/time-required-to-deal-with-construction-permits-days/algeria/niger/">Algeria vs Niger: Time required to deal with construction permits</a> — Statizoid

About this data

Indicator
Time required to deal with construction permits (days)
Unit
days
Source
World Bank, Doing Business project (http://www.doingbusiness.org/)
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
56 places, 447 data points, 2005–2012
Last refreshed

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.