Cabo Verde vs Seychelles: Time required to deal with construction permits

Cabo Verde
122 days
in 2012
Seychelles
126 days
in 2012
Cabo Verde rank
40th
Seychelles rank
37th

Time required to deal with construction permits over time

  • Cabo Verde
  • Seychelles
050100150200520082012

How they compare

Seychelles currently reports 126 days against 122 days in Cabo Verde, a difference of 4 days.

Across all 8 years both countries report, Seychelles has been ahead every year.

Cabo Verde ranks 40th and Seychelles ranks 37th of 50 countries.

Seychelles has averaged higher in every one of the 2 decades both report.

Head to head by decade

Decade Cabo Verde Seychelles Difference Ahead
2000s 122 days 126 days 4 days Seychelles
2010s 122 days 126.33 days 4.33 days Seychelles

Averages of every year both report within each decade.

Frequently asked questions

Which has higher time required to deal with construction permits, Cabo Verde or Seychelles?
Seychelles, at 126 days against 122 days in Cabo Verde as of 2012.
What is the difference in time required to deal with construction permits between Cabo Verde and Seychelles?
4 days, with Seychelles ahead.
How many years of comparable data are there for Cabo Verde and Seychelles?
8 years are reported by both, from 2005 to 2012.
How do Cabo Verde and Seychelles rank globally for time required to deal with construction permits?
Cabo Verde ranks 40th and Seychelles ranks 37th of 50 countries.
Where does this data come from?
World Bank, Doing Business project (http://www.doingbusiness.org/), published as Time required to deal with construction permits (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.

Individual pages

Share, cite or embed this page

Cite this page

Cabo Verde vs Seychelles: Time required to deal with construction permits. Statizoid, drawing on World Bank, Doing Business project (http://www.doingbusiness.org/). Retrieved 18 August 2026, from https://private-sector.statizoid.com/compare/time-required-to-deal-with-construction-permits-days/cabo-verde/seychelles/

Embed or link this data

Paste this into a page to link back to these figures. The data itself is free to reuse under CC BY 4.0 (World Bank Open Data); please keep the attribution.

<a href="https://private-sector.statizoid.com/compare/time-required-to-deal-with-construction-permits-days/cabo-verde/seychelles/">Cabo Verde vs Seychelles: Time required to deal with construction permits</a> — Statizoid

About this data

Indicator
Time required to deal with construction permits (days)
Unit
days
Source
World Bank, Doing Business project (http://www.doingbusiness.org/)
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
56 places, 447 data points, 2005–2012
Last refreshed

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.