Ghana vs Tanzania, United Republic of: Time required to deal with construction permits

Ghana
218 days
in 2012
Tanzania, United Republic of
206 days
in 2012
Ghana rank
13th
Tanzania, United Republic of rank
16th

Time required to deal with construction permits over time

  • Ghana
  • Tanzania, United Republic of
050100150200200520082012

How they compare

Ghana currently reports 218 days against 206 days in Tanzania, United Republic of, a difference of 12 days.

That makes Ghana's figure about 1.1 times Tanzania, United Republic of's.

Across all 8 years both countries report, Ghana has been ahead every year.

Ghana ranks 13th and Tanzania, United Republic of ranks 16th of 50 countries.

Ghana has averaged higher in every one of the 2 decades both report.

Head to head by decade

Decade Ghana Tanzania, United Republic of Difference Ahead
2000s 218 days 190 days 28 days Ghana
2010s 218 days 206 days 12 days Ghana

Averages of every year both report within each decade.

Frequently asked questions

Which has higher time required to deal with construction permits, Ghana or Tanzania, United Republic of?
Ghana, at 218 days against 206 days in Tanzania, United Republic of as of 2012.
What is the difference in time required to deal with construction permits between Ghana and Tanzania, United Republic of?
12 days, with Ghana ahead.
How many years of comparable data are there for Ghana and Tanzania, United Republic of?
8 years are reported by both, from 2005 to 2012.
How do Ghana and Tanzania, United Republic of rank globally for time required to deal with construction permits?
Ghana ranks 13th and Tanzania, United Republic of ranks 16th of 50 countries.
Where does this data come from?
World Bank, Doing Business project (http://www.doingbusiness.org/), published as Time required to deal with construction permits (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.

Individual pages

Share, cite or embed this page

Cite this page

Ghana vs Tanzania, United Republic of: Time required to deal with construction permits. Statizoid, drawing on World Bank, Doing Business project (http://www.doingbusiness.org/). Retrieved 25 August 2026, from https://private-sector.statizoid.com/compare/time-required-to-deal-with-construction-permits-days/ghana/tanzania/

Embed or link this data

Paste this into a page to link back to these figures. The data itself is free to reuse under CC BY 4.0 (World Bank Open Data); please keep the attribution.

<a href="https://private-sector.statizoid.com/compare/time-required-to-deal-with-construction-permits-days/ghana/tanzania/">Ghana vs Tanzania, United Republic of: Time required to deal with construction permits</a> — Statizoid

About this data

Indicator
Time required to deal with construction permits (days)
Unit
days
Source
World Bank, Doing Business project (http://www.doingbusiness.org/)
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
56 places, 447 data points, 2005–2012
Last refreshed

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.