Mozambique vs Zimbabwe: Time required to deal with construction permits
Mozambique
377 days
in 2012
Zimbabwe
614 days
in 2012
Mozambique rank
3rd
Zimbabwe rank
1st
Time required to deal with construction permits over time
- Mozambique
- Zimbabwe
How they compare
Zimbabwe currently reports 614 days against 377 days in Mozambique, a difference of 237 days.
That makes Zimbabwe's figure about 1.6 times Mozambique's.
The two have swapped places 1 time across 8 shared years of data; in 2005 it was Mozambique ahead.
Mozambique ranks 3rd and Zimbabwe ranks 1st of 50 countries.
Zimbabwe has averaged higher in every one of the 2 decades both report.
Head to head by decade
| Decade | Mozambique | Zimbabwe | Difference | Ahead |
|---|---|---|---|---|
| 2000s | 377 days | 482.8 days | 105.8 days | Zimbabwe |
| 2010s | 377 days | 614 days | 237 days | Zimbabwe |
Averages of every year both report within each decade.
Frequently asked questions
- Which has higher time required to deal with construction permits, Mozambique or Zimbabwe?
- Zimbabwe, at 614 days against 377 days in Mozambique as of 2012.
- What is the difference in time required to deal with construction permits between Mozambique and Zimbabwe?
- 237 days, with Zimbabwe ahead.
- How many years of comparable data are there for Mozambique and Zimbabwe?
- 8 years are reported by both, from 2005 to 2012.
- How do Mozambique and Zimbabwe rank globally for time required to deal with construction permits?
- Mozambique ranks 3rd and Zimbabwe ranks 1st of 50 countries.
- Where does this data come from?
- World Bank, Doing Business project (http://www.doingbusiness.org/), published as Time required to deal with construction permits (days). Statizoid refreshes it automatically from the source and publishes the full history for both places.
Individual pages
About this data
The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.