Dealing with construction permits: Time in Fiji
Fiji: Dealing with construction permits: Time was 141 days in 2019. ▬ Flat
Dealing with construction permits: Time in Fiji, 2005–2019
Source: World Bank. Measured in days.
Analysis
The most recent figure for dealing with construction permits: time in Fiji is 141 days, measured in 2019. That is the highest value across all 15 years on record.
That represents a change of unchanged over ten years.
Over the whole period, dealing with construction permits: time in Fiji peaked at 141 days in 2008 and was at its lowest, 135 days, in 2005.
Fiji ranks 89th of 185 countries on this measure, in the middle of the range.
Averages by decade
| Decade | Average | Lowest | Highest | Years |
|---|---|---|---|---|
| 2000s | 137.4 days | 135 days | 141 days | 5 |
| 2010s | 141 days | 141 days | 141 days | 10 |
Countries ranked near Fiji
- 87 Guinea-Bissau 143 days compare
- 88 Belize 142 days compare
- 90 Jamaica 140.5 days compare
- 91 Maldives 140 days compare
- 92 Costa Rica 138 days compare
More private sector data for Fiji
- Merchandise trade 70.6% (2025)
- Food imports 19.0% (2024)
- Manufactures imports 56.5% (2024)
- Merchandise imports 3.25 billion current US$ (2025)
- Food exports 64.3% (2024)
- Manufactures exports 15.5% (2024)
- Merchandise exports 1.13 billion current US$ (2025)
- Commercial service exports 2.04 billion current US$ (2024)
- Transport services 46.6% (2024)
- Computer, communications and other services 16.1% (2024)
Frequently asked questions
- What is dealing with construction permits: time in Fiji?
- Dealing with construction permits: time in Fiji was 141 days in 2019, according to the World Bank.
- What is the highest dealing with construction permits: time recorded in Fiji?
- The highest recorded value was 141 days in 2008.
- What is the lowest dealing with construction permits: time recorded in Fiji?
- The lowest recorded value was 135 days in 2005.
- How does Fiji rank for dealing with construction permits: time?
- Fiji ranks 89th out of 185 countries with data for 2019.
- Is dealing with construction permits: time rising or falling in Fiji?
- Over the last ten years it is unchanged. The long-run trend across the full record is flat.
- Where does this Fiji data come from?
- The figures come from the World Bank, published as part of Dealing with construction permits: Time (days). Statizoid updates them automatically from the source API.
Download this data
CSV · JSON — 15 observations, free to reuse under CC BY 4.0 (World Bank Open Data).
About this data
The time captures the median duration that local experts indicate is necessary to complete a procedure in practice. It is calculated in calendar days. The time estimates of all procedures are added to calculate the total time required to complete each procedure, taking into account simultaneity of processes. It is assumed that the minimum time required for each procedure is one day, except for procedures that can be fully completed online, for which the time required is recorded as half a day.