Dealing with construction permits: Time (days) (Time days) in Australia

Australia: Dealing with construction permits: Time was 120.5 days in 2019. ▼ Falling

Latest (2019)
120.5 days
Change on year
down 0.4%
World rank
116th
of 188 countries
All-time high
142 days
in 2005
All-time low
112 days
in 2009
Years of data
15
2005–2019

Dealing with construction permits: Time in Australia, 2005–2019

0501001502005201220192005: 142 days2006: 142 days2007: 142 days2008: 142 days2009: 112 days2010: 112 days2011: 112 days2012: 112 days2013: 112 days2014: 112 days2015: 112 days2016: 121 days2017: 121 days2018: 121 days2019: 120.5 days

Source: World Bank. Measured in days.

Analysis

In 2019, dealing with construction permits: time in Australia stood at 120.5 days.

That represents a change of down 0.4% on the previous year and up 7.6% over ten years.

Over the whole period, dealing with construction permits: time in Australia peaked at 142 days in 2005 and was at its lowest, 112 days, in 2009.

That places Australia 116th out of 188 countries with data for 2019, putting it in the middle of the range.

The long-run direction has been consistently falling across the 15 years of available data.

Dealing with construction permits: Time in Australia, year by year

Annual values for Dealing with construction permits: Time (days) in Australia, 2005 to 2019.
Year days Change
2005 142 days —
2006 142 days +0.0%
2007 142 days +0.0%
2008 142 days +0.0%
2009 112 days -21.1%
2010 112 days +0.0%
2011 112 days +0.0%
2012 112 days +0.0%
2013 112 days +0.0%
2014 112 days +0.0%
2015 112 days +0.0%
2016 121 days +8.0%
2017 121 days +0.0%
2018 121 days +0.0%
2019 120.5 days -0.4%

Australia compared with similar countries

  • Australia's 120.5 days is below the median for high income countries, which is 144.75 days, 83% of the median. (62 countries reporting)
  • Australia's 120.5 days is above the median for East Asia & Pacific, which is 103.67 days, 1.2× the median. (28 countries reporting)

Averages by decade

DecadeAverage LowestHighest Years
2000s 136 days 112 days 142 days 5
2010s 115.55 days 112 days 121 days 10

Countries ranked near Australia

  1. 113 Democratic Republic of Congo 122 days compare
  2. 114 Burkina Faso 121 days compare
  3. 114 Paraguay 121 days compare
  4. 117 Philippines 120 days compare
  5. 118 Mozambique 118 days compare
  6. 118 Nepal 118 days compare

See the full ranking of 188 places →

More private sector data for Australia

All data for Australia →

Frequently asked questions

What is dealing with construction permits: time in Australia?
Dealing with construction permits: time in Australia was 120.5 days in 2019, according to the World Bank.
What is the highest dealing with construction permits: time recorded in Australia?
The highest recorded value was 142 days in 2005.
What is the lowest dealing with construction permits: time recorded in Australia?
The lowest recorded value was 112 days in 2009.
How does Australia rank for dealing with construction permits: time?
Australia ranks 116th out of 188 countries with data for 2019.
Is dealing with construction permits: time rising or falling in Australia?
Over the last ten years it is up 7.6%. The long-run trend across the full record is falling.
Where does this Australia data come from?
The figures come from the World Bank, published as part of Dealing with construction permits: Time (days). Statizoid updates them automatically from the source API.

Download this data

CSV · JSON — 15 observations, free to reuse under CC BY 4.0 (World Bank Open Data).

Share, cite or embed this page

Cite this page

Dealing with construction permits: Time in Australia. Statizoid. Retrieved 07 October 2026, from https://private-sector.statizoid.com/stat/dealing-with-construction-permits-time-days/australia/

Embed or link this data

Paste this into a page to link back to these figures. The data itself is free to reuse under CC BY 4.0 (World Bank Open Data); please keep the attribution.

<a href="https://private-sector.statizoid.com/stat/dealing-with-construction-permits-time-days/australia/">Dealing with construction permits: Time in Australia</a> — Statizoid

About this data

Indicator
Dealing with construction permits: Time (days)
Unit
days
Source
World Bank
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
188 places, 2,751 data points, 2005–2019
Last refreshed

The time captures the median duration that local experts indicate is necessary to complete a procedure in practice. It is calculated in calendar days. The time estimates of all procedures are added to calculate the total time required to complete each procedure, taking into account simultaneity of processes. It is assumed that the minimum time required for each procedure is one day, except for procedures that can be fully completed online, for which the time required is recorded as half a day.