Time required to deal with construction permits in Kenya

Kenya: Time required to deal with construction permits was 125 days in 2012. ▼ Falling

Latest (2012)
125 days
Change on year
unchanged
World rank
38th
of 50 countries
All-time high
163 days
in 2005
All-time low
105 days
in 2008
Years of data
8
2005–2012

Time required to deal with construction permits in Kenya, 2005–2012

0501001502005200820122005: 163 days2006: 163 days2007: 130 days2008: 105 days2009: 125 days2010: 125 days2011: 125 days2012: 125 days

Source: World Bank, Doing Business project (http://www.doingbusiness.org/). Measured in days.

Analysis

The most recent figure for time required to deal with construction permits in Kenya is 125 days, measured in 2012.

The figure is down 23.3% over ten years.

Kenya ranks 38th of 50 countries on this measure, in the bottom quarter.

Averages by decade

DecadeAverage LowestHighest Years
2000s 137.2 days 105 days 163 days 5
2010s 125 days 125 days 125 days 3

Countries ranked near Kenya

  1. 35 Ethiopia 128 days compare
  2. 36 South Africa 127 days compare
  3. 37 Seychelles 126 days compare
  4. 38 Uganda 125 days compare
  5. 40 Cape Verde 122 days compare
  6. 41 Sao Tome and Principe 118 days compare

See the full ranking of 56 places →

More private sector data for Kenya

All data for Kenya →

Frequently asked questions

What is time required to deal with construction permits in Kenya?
Time required to deal with construction permits in Kenya was 125 days in 2012, according to World Bank, Doing Business project (http://www.doingbusiness.org/).
What is the highest time required to deal with construction permits recorded in Kenya?
The highest recorded value was 163 days in 2005.
What is the lowest time required to deal with construction permits recorded in Kenya?
The lowest recorded value was 105 days in 2008.
How does Kenya rank for time required to deal with construction permits?
Kenya ranks 38th out of 50 countries with data for 2012.
Is time required to deal with construction permits rising or falling in Kenya?
Over the last ten years it is down 23.3%. The long-run trend across the full record is falling.
Where does this Kenya data come from?
The figures come from World Bank, Doing Business project (http://www.doingbusiness.org/), published as part of Time required to deal with construction permits (days). Statizoid updates them automatically from the source API.

Download this data

CSV · JSON — 8 observations, free to reuse under CC BY 4.0 (World Bank Open Data).

About this data

Indicator
Time required to deal with construction permits (days)
Unit
days
Source
World Bank, Doing Business project (http://www.doingbusiness.org/)
Licence
CC BY 4.0 (World Bank Open Data)
Coverage
56 places, 447 data points, 2005–2012
Last refreshed

The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice.